This process will include the installation of five 24” diameter drilled piers reinforced with steel and filled with grout. Once the test piers have been installed and cured, they will begin load testing at the site which will continue for 3-4 weeks.
A map of the proposed parking deck location can be found here:
Parking Structure Layout
They have also created a website for the community to receive the latest updates, and the site will be updated monthly.